The latest build status for Meta’s Ohio and Louisiana AI campuses, and what remains future capacity.
Prometheus and Hyperion are Meta AI infrastructure projects in Ohio and Louisiana. Prometheus is under development with a 2026 operating target, while Meta expects Hyperion to begin coming online in 2028 and scale toward 5 gigawatts once complete. These targets describe future scale, not commissioned compute available today.
Memory trick: A city-sized construction plan describes possible future rooms, not desks available to rent today.
Prometheus and Hyperion are Meta AI infrastructure projects designed to support very large-scale compute. Prometheus is a planned 1-gigawatt cluster under development around New Albany, Ohio, with a 2026 operating target. Meta says Hyperion construction is well underway in Richland Parish, Louisiana; it is expected to begin coming online in 2028 and scale toward 5 gigawatts once complete.
As AI infrastructure grows, the planning unit changes. The market moves from thinking about servers, to data centers, to full campuses and regional infrastructure systems.
Individual hardware.
Many systems working together.
A facility supporting large deployments.
Multiple facilities and power systems operating as one large compute platform.
Prometheus and Hyperion help explain what happens when compute becomes campus-scale infrastructure. Any figures shown are illustrative calculations, not current quoted market prices.
Construction status and operating targets were rechecked on Sep 16, 2026. Secondary reporting is identified where Meta does not publish the same detail directly.
Meta says construction is well underway and gives the Richland Parish location, ownership structure, and approximately $27 billion development cost.
Meta describes Prometheus as a 1-gigawatt cluster under construction and expects Hyperion to begin coming online in 2028, with capacity scaling toward 5 gigawatts once complete.
Meta identifies Prometheus in New Albany, Ohio as an operation supported by its long-term energy strategy.
Local reporting attributes the construction status and operating target to a Meta spokesperson and Meta’s public project timeline.
Once AI infrastructure reaches multi-gigawatt scale, the challenge changes. The problem is no longer only adding more servers; it is coordinating power, buildings, cooling, networking, and operations across a much larger physical system.
Practical takeaway
Interpret multi-gigawatt campus plans by tracking power delivery, construction stages, cooling, equipment, commissioning, and workload readiness instead of treating total planned scale as live supply.
Decision check: translate a campus announcement into market supply only at the stage supported by evidence.